PROJECT DATE: 2025
LOCATION : ZONGULDAK
INDUSTRY : IRON AND STEEL

No:4 Coke Battery 3 rd phase C group benzol stripping unit civil, mechanical,piping,electrical and instrumentation works 

Scope of Services

Construction and installation of 4 tanks ,

Construction and installation of foundations for 22 exchangers (140 tons),

Construction and installation of foundations for 8 pumps (16 tons) ,

Construction and installation of foundations for 9 equipment (155 tons) ,

300 tons of steel fabrication and installation ,

36.000 WDI piping fabrication and installation ,

Instrumentation and cathodic protection works for 4 tanks , 

3000 m2 insulation works for tanks, equipment and piping,

Electrical & Instrumentation (E&I) works,

SUCCESSFULLY COMPLETED