AKSA
Yalova 1984 2 month
Erection of 1000 m3 spherical tank
TEKSTIPLIK A.S.
Edirne 1987 2 month
4 km of piping, pneumatic gibs conveying system and insulation.
DUSA-DUPONT / SABANCI / TEKFEN
Izmit 1989 8 month
Technological erection of industrial yarn plant (Nylon 66) 56 km piping, 1000 ton equipment erection, 5000 m2 ducting, 5000 m2 insulation, 300t steel construction.
KORTEKS
Bursa 1993 5 month
Piping works of Poly plant.
YALOVA ELYAF
Yalova 1993 - 94 6 month
Installation of fire fighting system.
SASA A.S.
Adana 1994 - 95 6 month
Equipment erection of piping of TPA and Glycol plants.
YALOVA ELYAF
Yalova 1995 9 month
Manufacturing and erection of 5000 m3 cylindrical storage tank.
YALOVA ELYAF
Yalova 1996 - 97
Equipment erection, piping, insulation, steel construction, painting works of new acrylic line.
SAKOSA
Kocaeli 1999 2 month
SAKOSA Fire fighting systems.
SAKOSA
Kocaeli 1999 4 month
SAKOSA duct works.
SAKOSA
Kocaeli 1999 3 month
SAKOSA Chip and Chip blender silos.
SAKOSA
Kocaeli 1999 3 month
SAKOSA Natural Gas System.
SAKOSA
Kocaeli 2000 5 month
Equipment and piping erection of SAKOSA Phase II extention project.
DUSA (KORDSA) ENDÜSTRİYEL İPLİK A.Ş.
Kocaeli 1999 - 2000 1 year
Mechanical erection of T-66 Industrial Yarn Manufacturing & Trading, Inc.
HOECSA
1998 ongoing
Mechanical Erection of yarn and tire cord factories.
HOECSA
1998 ongoing
70 of storage tanks, vessels and columns manufacturing and erection of yarn and tire cord factories. |