PETKIM / ALAMSAS
Yarimca 1983 2 month
Erection of cell walls of chlorine factory.
PETKIM / ALARKO
Aliaga 1983-84 21 month
Mounting of instrumentation and process control room for VCM factory.
ALPET / GURIS
Aliaga 1987 - 1988 12 month
Erection of 4 x 1600 m3 spherical propylene tanks & 5 km. piping.
YARPET / TEKFEN
Yarimca 1988 5 month
Erection of 2 x 1000 m3 spherical propylene tanks & 5 km. piping.
ALPET / GURIS
Aliaga 1988 - 1989 3 month
Erection of 1500 m3 spherical VCM tank & piping.
ALPET / GURIS
Aliaga 1989 1 month
Erection of daily VCM tank & piping. |