CHEMICAL

    PLASTIFAY
    Istanbul 1986 - 87 12 month

    15 km. piping, steel construction, instrumentation and insulating of F.A. distillation unit.


    TUGSAS / TEKFEN
    Gemlik 1987 - 88 11 month

    Piping, equipment erection, steel cons. insulation of demineralisation and waste water treatment unit.


    TUGSAS / GURIS
    Samsun 1987 - 88 4 month

    Manufacturing and erection of 2 x 2 500 m3 cylindrical tanks.


    BASF-SUMERBANK
    Gebze 1988 - 89 4 month

    Erection of sulfonisation and chlorine distribution units.


    KORUMA TARIM
    Izmit 1990 1 month

    Erection of cells of chlorine factory.


    KORUMA TARIM
    Izmit 1991 2 month

    Dismantling, transportation, erection and start-up of formulation mill.


    KORUMA TARIM
    Izmit 1991 - 92 12 month

    Design, civil works, manufacturing and erection of cylindrical storage tanks farm.


    BASF-SUMERBANK
    Gebze 1993 2 month

    Manufacturing and installation of 1 m3 liquid waste tank. (CS), manufacturing and erection of 25 m3 monomer storage tanks. (SS), manufacturing and erection of 50 m3 monomer storage tank. (CS).


    DOW TURKIYE A.S.
    Gebze 1998 - 99 5 month

    Mechanic, electric and instrumentation works of "System House Capacity Expansion Project."