CEMENT













    YEMEN CIMENTO / ALAMSAS-IHI
    &Izmit 1991 4 month

    Manufacturing of ducting and firing hood.

    LEBDA CEMENT / ENKA TEKNIK
    Libya 1994 3.5 month

    Manufacturing and erection of 225.000 m3/h electrofilter of Lebda Cement Plant.

    ASLAN CIMENTO / ALAMSAS
    Darica 1986 2 month

    Erection of dust filter.








    ASLAN CIMENTO / ALAMSAS
    Darica 1986 6 month

    Manufacturing of portable cement silos.

    ASLAN CIMENTO
    Darica 1987 4 month

    Manufacturing of compensators, gas ducts and furnace heads.

    Darica 1987 2 month

    Revision and rehabilitation works of 1987.

    Darica 1987 15 days

    Replacing of "Baumer" conveyor.

    Darica 1987 - 88 12 month

    Dimantling of 3 pre-heater column, 3 furnace, 4 cement mill, steel and, concrete construction (6700 t).

    Darica 1988 2 month

    Erection of Fuel-oil preheating system.

    Darica 1988 2 month

    Erection of Compressor unit and its piping.
    Darica 1989 1 month
    Revision and rehabilitation works of 1989.

    Darica 1991 1 month

    Revision and rehabilitation works of 1991.

    Darica 1992 1 month

    Manufacturing and erection of ducting work.

    Darica 1994 - 95 7 month

    Steel and concrete construction, conveyors design manufacturing and erection of cement and raw material feeding systems of mills